Find the developer or owner behind a data center project
Trace a new data center's owner, developer, or tenant from county deeds to shell LLCs, Secretary of State filings, air permits, and utility dockets.
To find the developer or owner behind a new data center project, open the site’s county parcel, read the deed to the LLC that bought the land, then look that LLC up in the state business database. You finish with a company name, its role and the record that shows it.
The maker of Wattlas, a tracker of US data centers that are not open yet, wrote this page.
Before you start
You need the project name or the site address, plus the county and state. The name you have may not be the owner’s. Data Hunter’s guide, updated 19 April 2026, says hyperscalers often build under shell LLCs with names like “Project Marvel” or “Project Jupiter” to obscure ownership during permitting. It adds that by the time a project is publicly named, it is often already 12 to 18 months into construction.
Roles to keep apart
Data Center Radar’s field guide, published 31 October 2026, defines the roles you will meet.
| Role | Description in the Radar guide |
|---|---|
| Owner | Commissions or holds an interest in the asset |
| Operator | Runs the facility |
| Tenant | Uses contracted space or capacity |
| Developer | Assembles the site and advances the development |
| Contractor | Delivers contracted scopes |
AI GridWatch says a campus has up to three separate parties: the operator, the owner (often a PE fund) and the tenant, who actually consumes the power. Radar says one company can hold several roles, but the overlap needs evidence. Do not assume the landowner is the eventual operator or that a hyperscale tenant owns the building.
Steps to trace the company
AI GridWatch gives this route from a shell LLC to an operator: county assessor or GIS parcel, the grantee LLC on the deed, the state Secretary of State business database, then the registered agent and principals. Steps 1 to 3 follow it.
- Open the county assessor or GIS parcel page for the site and find the deed. You should see the grantee, the party that received the land.
- Copy the grantee’s name from the deed exactly as written. AI GridWatch says land is bought through single-purpose shell LLCs and calls the LLC the join key back to county deed records. You should now hold one LLC name.
- Search the state Secretary of State business database for that LLC. The route ends at the registered agent and principals, the names to follow next. Data Center Radar says an unfamiliar legal entity is a reason to investigate the relationship, not a reason to swap in a better-known brand.
- Find the project’s rezoning application or special-use permit. Data Hunter’s guide says a proposed project has typically filed only one of these. Radar says a planning application may name a project company, landowner, agent or consultant, and that a site selector may represent an unnamed client. Copy the role the filing gives.
- Run the search “[county name] building permit search” and open the permit. Data Hunter’s guide says the general contractor and project address are listed on it, and suggests filtering by permit type “commercial new construction” or “industrial”. The same 19 April 2026 guide says a permit above 100,000 sq ft typically signals a hyperscale facility, and a project value above $100M is almost always a data center or semiconductor fab. Radar adds that a contractor on a permit is evidence about that permit and its work, not about the whole campus.
- Look up the utility interconnection filing with the regional grid operator, such as PJM, ERCOT or MISO. Data Hunter’s guide says every data center over a few megawatts must file one, that the filings are public, and that they reveal load size before construction begins. Match the load size to the project in your application and permit.
- Read the economic development announcement for the county or state. Data Hunter’s guide says these press releases name the operator or a shell LLC, capacity, capex and timeline. AI GridWatch’s megaproject table says announced investment and capacity figures are the developer’s own claims, repeated by trade press.
- Record each company with its role, the record that names it and that record’s date. Data Center Radar says to keep unresolved relationships visible instead of filling gaps with assumptions.
Names operators use on filings
AI GridWatch lists the entity names below for each operator. Compare them with the LLC from step 2.
| Operator | Names AI GridWatch lists |
|---|---|
| Land-acquisition shells Jet Stream LLC and Sharka LLC | |
| Meta | Codename shells Greater Kudu, Raven Northbrook, Stadion, Wobniar, Pinnacle Mountain |
| Microsoft | Project-name or generic “Holdings LLC” entities, less consistently codenamed |
| Amazon (AWS) | Vadata, Inc., AWS’s build/operating entity on many permits |
| Digital Realty | “Digital [City]/[Address] LLC” |
| QTS | “QTS … LLC” plus Blackstone holding entities |
| Vantage | Per-campus “Vantage … LLC” site entities |
| Switch | “Switch … LLC”; campuses branded “Primes” |
Trackers that list developers and owners
AI GridWatch and Follow the Money list the companies behind projects, and Data Hunter shows operator and contractor information for each site.
AI GridWatch
Its directory page has an operators and owners table with columns for operator, category, owner or PE parent, model and filing LLCs.
Follow the Money
Follow the Money, from No Conshy Data Centers, connects organizations named as backers in public records to Pennsylvania data center projects. Its organization categories include developer, landowner, owner or investor, and tech company or data center tenant. The workbook behind it is free to use under CC BY 4.0 with credit. Where public records do not name a developer, owner or investor it can confirm, the entry is listed under “Gaps in the record”.
Data Hunter
Data Hunter describes itself as a free, public, interactive map and directory of US data centers, with capacity, location, operator and contractor information for each site. Its guide says the map covers projects under shell LLC names, with the operator confirmed via permit cross-reference.
Wattlas for projects that are not open yet
Wattlas is a paid tracker of US data centers that are not open yet, with a free public US data center owners directory covering developers, operators, and hyperscalers across the country. Every pipeline project is tied to at least one official record: a permit, a zoning case, a utility filing or a state incentive agreement. A press release or a listing in another tracker alone does not get a project in. Each fact links to its source, so you can open the permit or filing.
For deeper patterns on codename filings, see Data center shell LLCs and project codenames or inspect three unlocked sample records. Pricing is published at /pricing/ and bought without a sales call.