Large load interconnection: definitions and the six steps

How large load interconnection works for US data centers: ERCOT, SPP, NYISO & MISO MW thresholds, the 6 study steps, and why queue requests slip.

Wattlas 11 Nov 2026 · Updated 27 Nov 2026 · 6 min
Campuses in the pipeline
1,082
Reported so far
155.7 GW
Moratoria in force
938

As of 27 Nov 2026

Large load interconnection is the process a transmission provider and a customer such as a data center use when the customer requests to connect to the grid, as RMI describes it (14 April 2026). The maker of Wattlas, a paid tracker of US data centers that are not open yet, wrote this page from the sources linked below.

How sources define a large load

PNNL’s September 2025 report for the US Department of Energy says the definition of a large load varies and proposes no firm size definition. It gives a range from a 5 MW distribution-connected data center to a “hyperscale” load of 500 MW or more. A white paper on emerging large loads with a NERC footer dated July 2025 includes only organizations that volunteered information and says its details are subject to change.

Body Source and date Threshold as stated
RMI RMI article, 14 April 2026 Loads above approximately 20 MW, such as data centers, require direct connection to the transmission system
SPP PNNL report, September 2025 (citing SPP 2025) 10 MW or more of peak demand if the point of interconnection is 69 kV or below; 50 MW if above 69 kV
ERCOT PNNL report, September 2025 Large load requirements at 20 MW or greater, with additional considerations at 75 MW or greater
ERCOT White paper, July 2025 75 MW or larger
NYISO White paper, July 2025 Interconnection studies for 10 MW or greater at 115 kV or above, or 80 MW or greater below 115 kV
NERC Large Loads Task Force PNNL report, September 2025 No size threshold

How MISO’s draft definition changed in 2026

MISO presented these drafts to stakeholders ahead of a planned tariff filing. A MISO document dated 21 May 2026 defines a Large Load Campus as load at a single site behind one or more Points of Withdrawal from the Transmission System, controlled by one entity or a group that coordinates the load profile. After 1 September 2026 it covers any new load, or any increase of 25 MW or more to existing load at a single site that results in aggregate demand of 50 MW or more. Load that already exceeds 50 MW on that date is covered by any increase of 25 MW or more above the value documented on it.

A 29 June 2026 working group deck quotes FERC’s show cause order, which says it appears reasonable to define a large load as a new commercial or industrial customer at a single site, with a peak load of 50 MW or greater, interconnecting above 69 kV and not part of a co-location arrangement.

In the 27 July 2026 deck the draft defines a Large Load as load with demand of 50 MW or more at a single substation behind one or more Points of Withdrawal, and excludes load associated solely with an Electric Storage Resource.

On requirements, the 21 May document says a campus linked to data centers, supercomputing centers or other uses meeting NERC’s Computational Load definition is subject to all of them, while other campuses may be exempted from some. The 29 June draft subjects all Large Load to Basic Facility Data, Modeling, Telemetry, Forecast Data and Audit requirements, and adds Phasor Measurement, Ride-Through and Ramp requirements for Computational Load.

Who files a large load interconnection request

Typically the large load customer first works with the local utility, and together they submit an interconnection request to the transmission owner, according to RMI. The transmission owner leads the processing and coordinates closely with the Regional Transmission Organization (RTO) where one exists. In MISO’s 29 June 2026 draft, a Large Load Customer must coordinate with the Transmission Owner where the Large Load’s Point of Withdrawal is located.

The white paper describes how individual operators handle these requests. For loads above its thresholds, NYISO performs a single System Impact Study, and smaller loads go entirely through the connecting transmission owner’s procedures, with NYISO not involved. In ERCOT, transmission service providers must submit interconnection studies that meet NERC Reliability Standard FAC-002-2 for each applicable large load.

The six steps RMI describes

RMI says the process varies by region and summarizes it in six conceptual steps.

  1. Preliminary inquiry and scoping: the customer submits a formal request giving the proposed location, size in megawatts, voltage level and desired in-service date, and the provider assesses feasibility.
  2. Interconnection request: if the project exceeds distribution system capabilities, the customer submits an interconnection request to the transmission provider.
  3. A viability study: the provider assesses viability with engineering judgment, without a full interconnection or system impact analysis, then gives preliminary cost estimates and expected timelines. To proceed, the customer pays additional study fees.
  4. System Impact Study: a detailed technical analysis of how the new load affects the broader transmission system, identifying required upgrades and assigning preliminary cost responsibility. RMI calls it the most critical step because it determines what must be built and who is responsible.
  5. Facilities Study: a full engineering plan with construction-level detail and more precise cost estimates and schedules.
  6. Agreement to proceed: once the studies are complete, the customer decides whether to execute the interconnection agreement and, in many cases, post significant financial security or deposits.

After the agreement, the project moves into detailed engineering, permitting and construction, with final testing before energization. RMI says the full process can take anywhere from several months to several years from initial request to full energization.

What a request shows about whether a data center will be built

A request gives the proposed location, size, voltage level and desired in-service date, according to RMI’s first step. RMI says the interconnection process does not assess whether enough generation exists to serve the new load, and that regulators set ongoing electricity costs separately. Once the studies are complete, the customer decides whether to execute an interconnection agreement. PNNL reports a surge in “speculative” interconnection requests by developers and lists reducing them among its proposed goals. For ERCOT, PNNL lists requirements that include demonstrating site control and paying study fees of at least $100,000.

How Wattlas tracks projects

Wattlas ties every project in the US data center pipeline to at least one official record: a permit, a zoning case, a utility filing or a state incentive agreement. A press release or a listing in another tracker alone does not get a project in. Every fact links to its source, so you can open the permit or filing. Stages come from records, not from announcements, and changes are dated. Capacity is shown where a record states it—see Data center megawatts explained, Phantom data centers: the record test, and US data center markets for grid-level context. Pricing is published at /pricing/ and you can compare platforms in the tracker comparison hub.

What is not known

The PNNL report and the white paper give ERCOT different thresholds, 20 MW and 75 MW, and the table shows each as stated. A November 2024 informal survey by a subgroup of NERC’s Large Loads Task Force asked what size should count as large. The white paper reports that “large” may be relative to other factors, such as the voltage at which the load connects.

MISO’s definition is a draft in the latest document used here, dated 27 July 2026. Its target for the tariff filing moved from 30 June 2026 in the 10 June 2026 deck to the second half of August 2026 in the 27 July deck. The 10 June deck also says stability assessment requirements are deferred to a future filing, likely later in 2026. What MISO filed, and when, is not covered here.

95 of 1,082 campuses in the pipeline are under construction, about one in 11Open this in the app

See the data behind this article, free

Create free account

Questions

How do utilities handle large load interconnection requests?

The customer works with the local utility and transmission owner to scope the site and requested MW, then moves through a viability screen, a System Impact Study that identifies required grid upgrades, a Facilities Study with engineering costs and schedules, and a binding interconnection agreement with financial security.

What MW size triggers a large load interconnection study?

Thresholds vary by grid operator: RMI cites roughly 20 MW for direct transmission connection, ERCOT applies large-load standards at 75 MW (with requirements starting at 20 MW), NYISO studies 10 MW+ at 115 kV or 80 MW+ below 115 kV, SPP uses 10 MW (<=69 kV) or 50 MW (>69 kV), and MISO's 2026 drafts center on 50 MW+.

What is the difference between a System Impact Study and a Facilities Study?

A System Impact Study models how the new data center load affects reliability across the transmission grid and identifies required substation or line upgrades. A Facilities Study follows with detailed construction-level engineering, cost estimates, and a build schedule.

How can large power users speed up grid interconnection for a new load?

Siting near existing high-voltage substations with spare transmission capacity, providing early site control and study deposits, phasing load ramp-up across years, or pairing with co-located or bridge generation can shorten wait times, though new transmission builds still set the final energization clock.