Ada moratorium
Ada, Ohio paused new data center approvals on 7 Apr 2026, citing zoning and rules and infrastructure. Checked 23 Nov 2026
Started 7 Apr 20268 of 17 months passedEnds 1 Sep 2027
The facts
- Applies to
- None; no companies have shown interest.
- Reason
- Precautionary: residents' concerns; no inquiries received; village infrastructure cannot supply large data centers; time to write zoning.
- Term
- Originally six months (to Oct. 7, 2026); extended by an additional twelve months from the effective date of Resolution 2026-109 (emergency, adopted Sept. 1, 2026)
- Legal basis
- Village of Ada Resolution 2026-101 (emergency) imposing a temporary moratorium on data centers and cryptocurrency mining centers; extended by Resolution 2026-109 (emergency)
- What happened next
- Village pursuing permanent legislation that would prohibit data centers (Planning Commission hearing Sept. 29, 2026).
Campuses in reach
Google Lima Data CenterAllen CountyAnnounced·GoogleProject Galaxy (AWS Sidney data center)Shelby CountySite permit·AmazonQTS Data CenterVan Wert CountySite permit·500 MWQts Datacenters Van WertVan Wert CountyAnnounced·QTSCMH071 CampusUnion CountySite permit·≈36–160 MWCMH086 CampusUnion CountySite permit·≈80–370 MW
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Ada votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.