In forceMoratorium

Adair County moratorium

Adair County, Iowa paused new data center approvals on 18 Mar 2026, citing specific project and infrastructure. It covers 1 tracked campus. Checked 23 Nov 2026

In force since 18 Mar 2026No end date on record

The facts

Applies to
Applied Digital interest in a 200 MW data center near Adair reported in Clarke County coverage; no Adair County project approval record captured.
Reason
Proposed 765 kV MISO transmission line, land negotiations in the Hebron area, and concern that data centers require large amounts of electricity and water.
Term
Until the Board imposes a permanent moratorium by resolution, passes an ordinance regulating the structures, or rescinds the temporary moratorium; no calendar end date (Resolution #2026-26).
Legal basis
Resolution #2026-26, "Resolution to Establish a Temporary Moratorium on the Construction of Data Centers, High-Density Computing Facilities, and Battery Storage Facilities in the Unincorporated Areas of Adair County, Iowa," adopted March 18, 2026 by unanimous 5-0 roll call.
What happened next
Supervisors continued reviewing a draft data center ordinance after adoption of the moratorium. The draft would require data-center equipment to be housed in permanent structures on foundations, not shipping containers or similar temporary structures (March 25, 2026 Western Iowa Today: "No action was taken on the ordinance today" — confirms ordinance was still in draft a week after the moratorium passed).

Know when Adair County votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (1 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near Adair County paused data centers?