In forceMoratorium

Baldwin Park moratorium

Baldwin Park, California paused new data center approvals on 4 Mar 2026 for 45 days, citing zoning and rules and land use. Checked 23 Nov 2026

In force since 4 Mar 2026No end date on record

The facts

Applies to
None identified.
Reason
Regional San Gabriel Valley wave of data center moratoria/bans (Monterey Park, El Monte, Montebello); city seeking time to study impacts and develop zoning standards for data center uses before any application is filed.
Term
Initial 45 days from 2026-03-04; on 2026-04-15 the City Council held a public hearing and extended the urgency ordinance for an additional 10 months and 15 days under Gov. Code section 65858 -- the standard first extension under that statute -- bringing the pause to one year from original adoption (through approximately 2027-03-04).
Legal basis
Urgency ordinance adopted under California Gov. Code section 65858, extended via public hearing on 2026-04-15 (exact extension ordinance number not located in this pass)
What happened next
45-day moratorium adopted and extended to approximately one year while the city develops data-center zoning standards.

Know when Baldwin Park votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near Baldwin Park paused data centers?