Bell County moratorium
Bell County, Kentucky paused new data center approvals on 2 Jul 2026, citing specific project and water use. Checked 23 Nov 2026
In force since 2 Jul 2026No end date on record
The facts
- Passed by
- Bell County Fiscal Court, 2 Jul 2026
- Term
- 2 years (24 months)
- What happened next
- Adopted two-year moratorium on data center construction.
- Applies to
- Murray Industries data-center project near Jellical Mine Road. Earlier WYMT reporting attributed a halt to land clearing. Kentucky Lantern reported that a contractor said he had been asked to clear land and visited the site before potentially moving equipment; it described extensive clearing before the moratorium. The project’s legal applicability and ultimate disposition remain unverified.
- Reason
- Adopted to halt a Murray Industries data center project after land clearing had begun, following resident opposition over water, noise, and road concerns raised at the June 26 first reading.
- Legal basis
- Bell County Fiscal Court moratorium on data center construction; instrument number not located in sources reviewed
Campuses in reach
No tracked campus within 80 km
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Bell County votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.