Bristol moratorium
Bristol, Tennessee paused new data center approvals, citing zoning and rules and infrastructure. It covers 2 tracked campuses. Checked 23 Nov 2026
The facts
- Term
- Two years; expires 2027-10-24 unless extended or replaced
- Applies to
- Establishment of new data centers within Bristol. The signed Ordinance 25-20 was not directly attached to either the February or March 2026 Planning Commission packets; Planning Commission discussion summaries describe a flat moratorium with no project-specific carve-outs but do not list any "exempt applications already filed" language gov agenda center or document center search
- Reason
- City planning records state Bristol's zoning ordinance was not equipped to handle data centers, including bitcoin mining and broader data mining; officials cited TVA, utility, water, wastewater, and siting questions.
- Legal basis
- Ordinance 25-20, imposing a temporary moratorium on establishment of data centers
- What happened next
- Planning Commission directed a drafting committee with City Council, BTES, water department, and planning staff representation to prepare a data center ordinance by 2026-07-01 for Planning Commission review and City Council approval.
Campuses in reach
No tracked campus within 80 km
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Bristol votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (2 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.