In forceMoratorium

Broken Arrow moratorium

Broken Arrow, Oklahoma paused new data center approvals on 15 Jun 2026, citing zoning and rules. It covers 2 tracked campuses. Checked 23 Nov 2026

In force since 15 Jun 2026No end date on record

The facts

Reason
Development of permanent data center regulations
Term
Until the earlier of December 31, 2026, or adoption of permanent regulations, with a possible extension totaling no more than six additional months
Legal basis
Ordinance No. 3929 (City of Broken Arrow), pausing new rezonings, special/conditional use permits, site plans, building permits, certificates of occupancy, and other approvals for data center uses; exempts vested projects, accessory uses, and facilities of 5 MW or less

Know when Broken Arrow votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (2 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near Broken Arrow paused data centers?