Broken Arrow moratorium
Broken Arrow, Oklahoma paused new data center approvals on 15 Jun 2026, citing zoning and rules. It covers 2 tracked campuses. Checked 23 Nov 2026
In force since 15 Jun 2026No end date on record
The facts
- Reason
- Development of permanent data center regulations
- Term
- Until the earlier of December 31, 2026, or adoption of permanent regulations, with a possible extension totaling no more than six additional months
- Legal basis
- Ordinance No. 3929 (City of Broken Arrow), pausing new rezonings, special/conditional use permits, site plans, building permits, certificates of occupancy, and other approvals for data center uses; exempts vested projects, accessory uses, and facilities of 5 MW or less
Campuses in reach
Citadel FacilityTulsa CountySite permit·Citadel Asset VenturesATMOSS Data CenterWagoner CountySite permit·AtmossAcacia Facility OSGMuskogee CountySite permit·Acacia House GroupCore Scientific: Muskogee 1Muskogee CountySite permit·Core ScientificGoogle Muskogee County CampusMuskogee CountyAnnounced·GooglePioneer FacilityMuskogee CountySite permit·Pioneer Trail
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Broken Arrow votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (2 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.