City of Cascade moratorium
City of Cascade, Iowa paused new data center approvals on 22 Jun 2026, citing specific project and zoning and rules. Checked 23 Nov 2026
In force since 22 Jun 2026No end date on record
The facts
- Passed by
- Cascade City Council, 22 Jun 2026
- Term
- 12 months
- Applies to
- Planned Simple Mining data center in Cascade's industrial park (redacted agreement with Cascade Economic Development Corp.).
- Reason
- Potential data center development (Simple Mining) discussed with the Cascade Economic Development Corp.; residents sought time for ordinances and public input.
- Legal basis
- Cascade City Council Resolution #57-26 approving a 12-month moratorium on data center construction within city limits.
Campuses in reach
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when City of Cascade votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.