EndedMoratorium

Cromwell moratorium

Cromwell, Connecticut paused new data center approvals, citing zoning and rules and specific project. The pause has ended. It covers 1 tracked campus. Checked 23 Nov 2026

The facts

Term
Proposed 12 months
Applies to
An unnamed prospective data center applicant, described by Commissioner Cannata as having worked with the town for approximately nine months and secured an option on a property, was cited during discussion; no formal application has been filed.
Reason
regulatory_gap: the town's zoning regulations have no definition or standards for a data center use; the moratorium proposal was introduced to pause any data center application while regulations are developed alongside a broader, already-contracted zoning-regulations rewrite (consultant IMEG). Commissioner Cannata opposed the moratorium, citing an unnamed prospective applicant who has worked with the town for nine months and already secured a property option.
Legal basis
Proposed text amendment Application #26-25 to Cromwell Zoning Regulations Section 4.2.E. for a 12-month data center moratorium; the Commission denied the application on September 24, 2026, after a public hearing.
What happened next
The original 12-month Application #26-25 remains recorded as rejected. October 20 minutes establish acceptance and hearing scheduling for Application #26-37, not adoption of its rules or a moratorium. November 5 agenda item 9(a) is discussion of a potential moratorium, not an adoption record; subsequent minutes and proposal text remain required.
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo

Know when Cromwell votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (1 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near Cromwell paused data centers?