In forceMoratorium

Desert Hot Springs moratorium

Desert Hot Springs, California paused new data center approvals on 16 Jun 2026 for 45 days, citing zoning and rules and land use. Checked 23 Nov 2026

In force since 16 Jun 2026No end date on record

The facts

Reason
Pause on licenses, permits, entitlements, and land-use approvals for data centers and similar high-intensity computing uses while the city studies whether, where, and under what standards such uses should be allowed; no specific data center application was reported pending
Term
Initial 45 days from 2026-06-16, according to the city staff report; July 23 reporting describes a unanimous extension of 22 months and 15 days. The proposed city text uses a July 7 anchor but contains a conflicting six-month recital; the final operative anchor and endpoint remain unverified.
Legal basis
Interim urgency moratorium ordinance, adopted and extended under California Gov. Code section 65858

Campuses in reach

No tracked campus within 80 km

The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo

Know when Desert Hot Springs votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near Desert Hot Springs paused data centers?