Dover moratorium

Dover, Delaware paused new data center approvals on 12 Oct 2026, citing zoning and rules and grid and power. It covers 1 tracked campus. Checked 23 Nov 2026

In force since 12 Oct 2026No end date on record

The facts

Applies to
None named; city officials said they have been approached about at least one small-to-medium data center project but declined to identify it.
Reason
Multiple inquiries about 'Large Energy Use Facilities' (data centers meeting defined MW/load thresholds); city wants time to study electrical capacity, ratepayer cost allocation, infrastructure, land use, environmental standards, and economic impact before adopting permanent regulations
Term
Eighteen months from the effective date, unless sooner repealed; Council may extend by ordinance upon findings that additional study remains necessary. Adopted text section3 states immediate effect upon adoption; section8 supplies the term. Later amendment, repeal or extension remains unchecked.
Legal basis
Ordinance 2026-14, reproduced as adopted in official October12,2026 Council minutes pages41-43, following September28 first reading. Section3 states immediate effect upon adoption. The dated adoption minutes supersede the older undated register status as evidence of the October12 action. The minutes include a mayoral approval statement on page44 but no handwritten execution signatures; separate signed/enrolled copy and later actions are not established.

Know when Dover votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (1 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.