Fairfield moratorium
Fairfield, Alabama paused new data center approvals on 27 Jul 2026 for 6 months, citing zoning and rules and specific project. Checked 23 Nov 2026
Started 27 Jul 20264 of 6 months passedEnds 23 Jan 2027
The facts
- Legal basis
- Ordinance 1174
- Applies to
- Exempts 7199 and 7160 Aaron Aronov Drive (site of the disclosed Patmos colocation data center proposal reported 2026-07-22)
- Reason
- Pause on new data centers, data center support facilities, and material expansions; exempts two specified parcels at 7199 and 7160 Aaron Aronov Drive and preserves vested rights and existing lawful operations
- Term
- 180-day prospective moratorium beginning on the ordinance's effective date (publication/posting date not located)
Campuses in reach
Blue Cross and Blue Shield of Alabama Data CenterJefferson CountySite permit·≈7–31 MWAlabama Data Center (10015)Jefferson CountySite permit·Bellsouth Telecommunications LLC Dba at T AlabamaNebius Birmingham Data CenterJefferson CountyAnnounced·300 MWDigihost: AL Site: Phase 1 and 2Shelby CountyAnnounced·Digi Power XChildersburg Data CenterTalladega CountySite permit·500 MW
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Fairfield votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.