Gordon County moratorium
Gordon County, Georgia paused new data center approvals on 3 Feb 2026, citing zoning and rules. Checked 23 Nov 2026
Started 3 Feb 202610 of 12 months passedEnds 29 Jan 2027
The facts
- Passed by
- Board of Commissioners, 3 Feb 2026
- Reason
- regulatory_gap
- Term
- Extended through 2027-01-29
- Legal basis
- Board of Commissioners motion adopting a data center moratorium on 2026-02-03; extended by resolution adopted at the 2026-07-07 regular meeting (agenda item 11: 'resolution extending a temporary moratorium relating to Data Centers'), alongside a separate anaerobic digestion facilities moratorium extension. Resolution numbers not published.
- What happened next
- Board of Commissioners extended its temporary moratoria on data centers (and anaerobic digestion facilities) through 2027-01-29
Campuses in reach
Digital Realty Stilesboro campusBartow CountyZoning·1,300 MWKingston Technology HubBartow CountyZoning·150 MWProject IndoBartow CountyZoning·200 MWSwitch Atlanta North - The KEEP 2.0Bartow CountySite permit·1,200 MWCore Scientific: Dalton 4Whitfield CountySite permit·Core ScientificIntegra SPV A/B/C (subleased to CoreWeave)Whitfield CountyAnnounced·Integra
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Gordon County votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.