ProposedMoratorium

Halifax County moratorium

Halifax County, North Carolina has proposed a pause on new data center approvals, citing zoning and rules and specific project. It covers 1 tracked campus. Checked 23 Nov 2026

The facts

Term
Not yet set
Applies to
Quiet Data Centers Halifax AI data center, 301 Industrial Site (county attorney warned a moratorium could affect the existing agreement).
Reason
Zoning ordinance does not regulate data centers; Quiet Data Centers Halifax 88 MW AI project at the county-owned 301 Industrial Site near Enfield
Legal basis
Proposed Halifax County data-center moratorium under N.C.G.S. 160D-107; the originally scheduled October 19, 2026 regular meeting was canceled.
What happened next
The originally scheduled October 19 regular meeting was canceled; a later news report describes a postponed data-center hearing but gives conflicting November dates. No adoption is established.

Know when Halifax County votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (1 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near Halifax County paused data centers?