Hitchcock County moratorium

Hitchcock County, Nebraska paused new data center approvals on 3 Feb 2025, citing zoning and rules and environment. The pause has ended. Checked 23 Nov 2026

Started 3 Feb 2025Ended

The facts

Term
One year or until updated zoning regulations were adopted, whichever was less
Applies to
Steven R. Fries data mining conditional use request was denied on 2025-01-21 before the moratorium. MB Club LLC later received conditional use approval for a data center on 2025-10-06.
Reason
Existing zoning did not adequately address data centers and crypto mining in AG-G and RCI districts. The resolution cited energy consumption, cooling and environmental footprint concerns, land-use impacts, and the need to study countywide zoning controls.
Legal basis
Resolution #2025-7, Temporary Moratorium on Data Centers and Crypto Mining Facilities
What happened next
Resolution #25-9 amended county zoning after a 2025-03-17 public hearing. The framework allows data centers and crypto mining through conditional use in AG-G and RCI districts and addresses I district standards. Resolution #25-19 approved MB Club LLC's conditional use with an impact easement requirement. Resolution #25-9 was adopted March 17, 2025, with amendments effective May 1, 2025.

Campuses in reach

No tracked campus within 80 km

The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo

Know when Hitchcock County votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.