Lamar County moratorium
Lamar County, Georgia paused new data center approvals on 16 Sep 2025, citing specific project and zoning and rules. It covers 1 tracked campus. Checked 23 Nov 2026
In force since 16 Sep 2025No end date on record
The facts
- Applies to
- AWS-linked 985-acre development site
- What happened next
- Code modernization including data-center treatment
- Reason
- Industrial and commercial zoning needed updating; county learned AWS bought about 985 acres for about $270 million
- Term
- 180 days (Resolution 2025-18), with an internal staff goal of completing the underlying code rewrite within 90 days; subsequently extended as to data centers specifically by Resolution 26-03 (on or about 2026-03-17). A secondary register reports a further September 15, 2026 extension for up to 180 days or until zoning revisions are adopted; the signed extension and exact operative end require verification.
- Legal basis
- Lamar County Resolution 2025-18, 'Moratorium on Commercial and Manufacturing Development,' adopted September 16, 2025; extended as to data centers by Resolution 26-03, adopted on or about March 17, 2026. A secondary register reports a further data-center extension under Resolution 2026-15 on September 15, 2026; the signed resolution was not recovered.
Campuses in reach
Rumble Technology ParkMonroe CountyAnnounced·≈670–3,100 MWTrammell Crow Forsyth CampusMonroe CountyAnnounced·≈1,500–6,900 MW75 South Data Center CampusSpalding CountyZoning·HillwoodWallace Jackson Data Center CampusSpalding CountyZoning·≈620–2,900 MWAmazon Web Services Butts County data center campusButts CountyAnnounced·AmazonRiver ParkButts CountyAnnounced·River Park Industrial
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Lamar County votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (1 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.