Logan County moratorium
Logan County, Colorado paused new data center approvals on 21 Oct 2025 for 6 months, citing specific project and zoning and rules. The pause has ended. Checked 23 Nov 2026
Started 21 Oct 2025EndedEnded 19 Apr 2026
The facts
- Legal basis
- Resolution 2025-25
- Applies to
- County Commissioners' October 14, 2025 work-session minutes record a briefing by developer Blake Marcus (Granite Renewables) and consultant Ben Gager (SWCA Environmental Consultants) describing a proposed project east and west of County Road 9 (approximately 21 miles northwest of Sterling) at close to 2 GW nameplate capacity, including 1 GW of on-site natural gas generation, 630 MW of solar as ancillary power, and 1,800 MWh of battery storage. Commissioner Yahn noted the moratorium had already been planned before this specific proposal surfaced. As of a January 2026 hearing, commissioners stated no formal permit application had yet been received.
- Reason
- County needed time to draft regulations before accepting or processing applications for data center, battery, solar, and wind facilities; meeting records cited grid, infrastructure, agricultural land, and land use compatibility concerns.
- Term
- 180 days as adopted; the data center, battery and solar components were rescinded effective February 17, 2026, and the wind component was rescinded effective April 7, 2026.
- What happened next
- Resolution 2026-5 adopted Data Center Facility regulations. The county planning page lists Resolution 2026-5 among amended regulations effective 2026-02-17 and 2026-04-07.
Campuses in reach
No tracked campus within 80 km
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Logan County votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.