Logan County moratorium
Logan County, Illinois paused new data center approvals on 19 May 2026, citing specific project and zoning and rules. The pause has ended. It covers 1 tracked campus. Checked 23 Nov 2026
Started 19 May 2026Ended
The facts
- Passed by
- County Board, 19 May 2026
- Applies to
- Hut 8 Corp.'s proposed 'Logan Prairie Data Center' (~500 MW, originally on ~250 acres, later refiled for 720 acres) near Latham, IL; a ~$5B project. Hut 8 has also been in talks with the Village of Latham about possible annexation, which could remove the site from county zoning jurisdiction.
- Reason
- Response to Hut 8 Corp.'s proposed ~500 MW 'Logan Prairie' data center near Latham; residents sought time to study the project and adopt safeguards before the county acted on Hut 8's land-use application.
- Term
- 12-month moratorium (approved 2026-05-19) intended to run through approximately 2027-05-19, but declared procedurally invalid and unenforceable by the State’s Attorney on 2026-06-18. As of an Aug. 4, 2026 committee meeting, the Board was drafting a replacement moratorium (covering data centers exceeding 100 MW) and had submitted it to the State's Attorney for review; as of a Sept. 17-18, 2026 report, the Board had not adopted a new moratorium and was instead advancing 18 amendments to its permanent data-center zoning ordinance.
- Legal basis
- 12-month moratorium approved by County Board vote 2026-05-19; declared invalid by Logan County State's Attorney Bradley Hauge on 2026-06-18 because it was not referred to the Zoning Board of Appeals for advisory review or subjected to public hearings before final passage, as required by county procedure.
- What happened next
- The county's attempt to pause data-center applications while it developed permanent zoning was defeated on procedural grounds; as of this research pass the county had not re-adopted a valid moratorium and was instead pursuing amendments to a permanent data-center zoning ordinance while Hut 8's rezoning application proceeds.
Campuses in reach
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Logan County votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (1 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.