Madison County moratorium
Madison County, Georgia paused new data center approvals on 3 Aug 2026, citing zoning and rules. Checked 23 Nov 2026
Started 3 Aug 20264 of 7 months passedEnds 22 Feb 2027
The facts
- Passed by
- Madison County Board of Commissioners, 3 Aug 2026
- Applies to
- None named
- Reason
- County needs time to amend development codes, subdivision regulations or zoning for data centers; statewide concern
- Term
- 30 days from 2026-08-03; superseded by a further moratorium adopted 2026-08-31 running through 2027-02-22 (about 175 days) per Main Street News, though a Sept. 1 radio report described the Sept. 1 vote as extending it 'for another 180 days' -- the two accounts do not reconcile exactly.
- Legal basis
- Madison County Board of Commissioners moratorium actions (30-day moratorium, early August 2026; extended/readopted 2026-08-31); instrument numbers not published
- What happened next
- Commissioners adopted a 30-day data center moratorium and then extended it about 180 days on 2026-08-31.
Campuses in reach
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Madison County votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.