Marysville moratorium
Marysville, Washington paused new data center approvals on 13 Jul 2026, citing zoning and rules and land use. Checked 23 Nov 2026
In force since 13 Jul 2026No end date on record
The facts
- Legal basis
- Ordinance No. 3381; RCW 36.70A.390 interim zoning control
- Reason
- Study period covers siting, public safety, land-use compatibility, water and sewer planning, utility rates, and permanent code amendments.
- Term
- Six-month pause on acceptance, processing, and approval of land-use and permit applications for facilities whose principal use is digital-data processing, storage, management, or transmission; incidental server equipment supporting another principal use is excluded. Public hearing required within 60 days.
Campuses in reach
No tracked campus within 80 km
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Marysville votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.