In forceMoratorium

Morristown moratorium

Morristown, Vermont paused new data center approvals on 31 Aug 2026, citing zoning and rules and grid and power. Checked 23 Nov 2026

In force since 31 Aug 2026No end date on record

The facts

Passed by
Morristown Select Board, 31 Aug 2026
Term
Two years from adoption, as an interim zoning bylaw
Applies to
None named; officials and residents confirmed no data center has been proposed in Morristown and few parcels are large enough to host one, but the board called the moratorium precautionary.
Reason
Town bylaws are silent on data centers and 'high-impact uses'; board wants time for the planning commission to study electric-grid, water, noise, and hazardous-waste impacts before any application is filed, prompted in part by community reaction to a separate large industrial-park/quarry proposal
Legal basis
Interim zoning bylaw adopted unanimously by the Morristown Select Board and Village of Morrisville Board of Trustees, dated 2026-08-31, following a selectboard proposal and two public hearings in August 2026
What happened next
Adopted unanimously by the Select Board and Village Board of Trustees on 2026-08-31 after a public hearing with dozens of residents, most supportive; Morristown is the third Vermont community (after Royalton's permanent five-year ban and South Burlington's zoning amendment) to restrict data centers.

Campuses in reach

No tracked campus within 80 km

The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo

Know when Morristown votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.