Oldham County Fiscal Court moratorium
Oldham County Fiscal Court, Kentucky paused new data center approvals for 5 months, citing specific project and zoning and rules. Checked 23 Nov 2026
The facts
- Term
- 150 days initially; later extended until data center regulations are approved
- Legal basis
- Ordinance KOC 25-910-508; extension KOC 25-910-520
- Applies to
- Project Lincoln / OC Data Center proposal near La Grange; reporting describes a withdrawn proposal after intense public pushback
- Reason
- Increased data center siting interest; infrastructure, utility capacity, energy use, land use, and environmental sustainability concerns; zoning rules did not adequately address data centers
- What happened next
- Data-center zoning regulations KOC 26-920-38 were adopted October 6, 2026; the effect on the earlier moratorium remains to be verified.
Campuses in reach
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Oldham County Fiscal Court votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.