EndedMoratorium

Putnam County moratorium

Putnam County, Georgia paused new data center approvals on 7 Aug 2026, citing zoning and rules and water use. The pause has ended. It covers 1 tracked campus. Checked 23 Nov 2026

Started 7 Aug 2026EndedEnded 17 Nov 2026

The facts

Passed by
Putnam County Board of Commissioners, 7 Aug 2026
Applies to
None named; two existing large solar fields unaffected
Term
Initially August 7 to November 6, 2026; extended until November 17, 2026.
Reason
Need to study and adopt regulations for data centers, solar and battery storage; public concern for Lake Sinclair and water resources
Legal basis
Putnam County Board of Commissioners Resolution 2026.8.7, adopted August 7, 2026; county reports extension October 21, 2026.
What happened next
Commissioners adopted a three-month moratorium on data centers, BESS and solar farms while revising the county's draft ordinance.

Know when Putnam County votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (1 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near Putnam County paused data centers?