Richmond moratorium
Richmond, California paused new data center approvals on 15 Sep 2026 for 45 days, citing zoning and rules and water use. Checked 23 Nov 2026
Started 15 Sep 20262 of 24 months passedEnds 15 Sep 2028
The facts
- Applies to
- None; city reported no pending data center applications.
- Reason
- City's municipal code does not specifically define or regulate data centers; council directed staff in April 2026 to return with a proposed moratorium; concerns over electricity/water use, noise, air quality, and the city's limited industrial land.
- Term
- Initial 45-day moratorium under Ordinance 13-26 N.S.; Ordinance 14-26 N.S. extends it by 22 months and 15 days, with an explicit end through September 15, 2028 unless terminated earlier.
- Legal basis
- Urgency Ordinance 13-26 N.S. adopted September 15, 2026; amended, restated and superseded by Urgency Ordinance 14-26 N.S., adopted October 20, 2026, extending the same moratorium under Government Code section 65858.
- What happened next
- 45-day urgency moratorium adopted while staff studies potential regulations and permanent zoning standards for data centers.
Campuses in reach
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Richmond votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.