Russellville moratorium
Russellville, Arkansas paused new data center approvals on 16 Jul 2026, citing zoning and rules. It covers 1 tracked campus. Checked 23 Nov 2026
In force since 16 Jul 2026No end date on record
The facts
- Passed by
- City Council, 16 Jul 2026
- Reason
- Pause on acceptance, processing, and approval of applications for data center development, construction, or siting within city limits; officials said no active data center proposal was known
- Term
- Six months as reported after amendment from an 18-month proposal; exact original wording, anchor and any earlier termination condition not verified.
- Legal basis
- City Council ordinance (instrument number not confirmed); creates a temporary committee to recommend regulations
- What happened next
- A six-month moratorium and regulatory committee were reported; later legal disposition is unverified.
Campuses in reach
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Russellville votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (1 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.