South Hutchinson moratorium
South Hutchinson, Kansas paused new data center approvals on 26 May 2026, citing zoning and rules and land use. Checked 23 Nov 2026
In force since 26 May 2026No end date on record
The facts
- Passed by
- South Hutchinson City Council, 26 May 2026
- Applies to
- None identified in sources retrieved.
- Reason
- A surge of companies proposing data centers nationally prompted the city to act proactively and cautiously before creating permanent rules; this was reported as the first pause on data center/BESS development in the eastern part of Reno County.
- Term
- One year, reported by the Citizen Journal as running from website publication; the original ordinance and publication date have not been independently verified.
- Legal basis
- The Citizen Journal reports South Hutchinson City Council adopted Ordinance 26-05 on May 26, 2026 by a 4-0 vote. The original ordinance and publication have not been independently verified.
- What happened next
- One-year pause on data center and battery energy storage system development within South Hutchinson city limits and its extraterritorial zoning jurisdiction, directing the planning commission and staff to review zoning regulations, research other municipalities' standards, and report findings by the end of the moratorium period.
Campuses in reach
No tracked campus within 80 km
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when South Hutchinson votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.