In forceMoratorium

South Point moratorium

South Point, Ohio paused new data center approvals on 5 May 2026, citing specific project and zoning and rules. Checked 23 Nov 2026

In force since 5 May 2026No end date on record

The facts

Term
Six months
Applies to
StrataX micro data center concept (solar plus battery storage) presented by Dean Green of Grain Consulting on 2026-04-07 for a site in South Point.
Reason
A presentation by a consultant for StrataX, a renewable-powered 'micro' data center developer interested in a site in the village industrial park (fly-ash field). Council wanted time to study legal, fiscal and health issues and revenue capture.
Legal basis
Resolution 26-04 imposing a moratorium on AI data centers, adopted May 5, 2026 after amendment to six months; operative signed text and effective date not retrieved.
What happened next
Study of legal options (zoning, reporting, siting conditions, revenue-sharing) for AI and micro data centers.

Know when South Point votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near South Point paused data centers?