In forceMoratorium

Springfield moratorium

Springfield, Ohio paused new data center approvals on 14 Jul 2026, citing zoning and rules. It covers 3 tracked campuses. Checked 23 Nov 2026

In force since 14 Jul 2026No end date on record

The facts

Passed by
City Commission, 14 Jul 2026
Term
6 months
Legal basis
City Commission ordinance, passed 5-0 on second reading; Ordinance 159-26
Applies to
The Springfield News-Sun reported that a data center then under construction was not affected. The report separately describes a 5C Group conversion at 601 Benjamin Drive; it does not explicitly identify the unaffected facility as that project.
Reason
City study of 'High-Density Computing Facilities' as a land use before permitting is resumed
What happened next
City Commission passed Ordinance 159-26 by a 5-0 vote after its second reading, imposing a six-month moratorium on the establishment, development, processing, review, and approval of High-Density Computing Facilities

Know when Springfield votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (3 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near Springfield paused data centers?