Town of Cary moratorium
Town of Cary, North Carolina paused new data center approvals on 27 Aug 2026, citing zoning and rules and grid and power. It covers 2 tracked campuses. Checked 23 Nov 2026
In force since 27 Aug 2026No end date on record
The facts
- Applies to
- None named; Cary hosts some smaller data center operations.
- Reason
- Cary's Land Development Ordinance does not define data centers; concerns about electricity demand, cooling water, generator and cooling noise, stormwater, tree canopy and air quality
- Term
- 18 months (to about 2028-02-27); staff schedule targets a Council decision on a permanent ordinance in February 2028
- Legal basis
- Ordinance Establishing a Temporary 18-month Moratorium on the Acceptance, Processing, and Approval of Development Applications for Data Centers, cryptocurrency mining operations and associated uses in Cary's planning jurisdiction (N.C.G.S. 160D-107); ordinance number not located
- What happened next
- 18-month moratorium; ordinance hearing anticipated October 2027 and Council decision February 2028.
Campuses in reach
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Town of Cary votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (2 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.