Vance County moratorium
Vance County, North Carolina paused new data center approvals on 14 Sep 2026 for 2 months, citing specific project and zoning and rules. The pause has ended. It covers 1 tracked campus. Checked 23 Nov 2026
Started 14 Sep 2026EndedEnded 13 Nov 2026
The facts
- Applies to
- Natelli Holdings 900 MW data center campus (Technology Lane / U.S. 158).
- What happened next
- 60-day moratorium pending UDO text amendment.
- Reason
- Natelli Holdings filed a preliminary plan for a 900 MW, 12-building data center campus on ~530 acres along U.S. 158 while the county revises its UDO data center rules
- Term
- 60 days: terminates 2026-11-13 or upon adoption of an amendment to the zoning ordinance's data center requirements
- Legal basis
- Vance County 60-day data center moratorium (number not located), N.C.G.S. 160D-107; the legal notice advertised 60 days, so a 6-month motion was ruled out of order
Campuses in reach
Microsoft AVC19 Data Center Auxiliary SiteMecklenburg CountySite permit·MicrosoftMicrosoft Corp - AVC17 DatacenterMecklenburg CountySite permit·≈120–260 MWMicrosoft Hillcrest CampusMecklenburg CountySite permit·MicrosoftMicrosoft LVL-16 Datacenter CampusMecklenburg CountyAnnounced·MicrosoftTecfusions Clarksville LLCMecklenburg CountySite permit·300 MWDuke University Gpu Data CenterDurham CountyConstruction·3 MW
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Vance County votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (1 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.