Westerly moratorium
Westerly, Rhode Island paused new data center approvals on 27 Jul 2026, citing zoning and rules and land use. Checked 23 Nov 2026
In force since 27 Jul 2026No end date on record
The facts
- Applies to
- None named; the town manager told the council the ordinances are 'currently silent on data centers' and the pause is meant to give the zoning side time to draft rules before any application could vest.
- Reason
- Town's ordinances and zoning regulations are silent on data centers; officials anticipate data center applications given the town's undeveloped land near water bodies and wanted time to draft siting/zoning rules before any application could vest
- Term
- One year upon passage, or as otherwise provided by the Town Council by ordinance; effective immediately upon passage
- Legal basis
- Town of Westerly ordinance 'AN ORDINANCE IMPOSING A ONE-YEAR MORATORIUM ON ALL DATA CENTERS,' adding a new Data Center Moratorium section to the Westerly Code of Ordinances; noticed for public hearing 2026-07-27, adopted the same night by voice vote
- What happened next
- Adopted by voice vote after a public hearing at the July 27, 2026 regular Town Council meeting; no recorded opposition.
Campuses in reach
The ordinance text and each campus's filingsOrdinance text and filingsStart Pro · $299/mo
Know when Westerly votes
Check your email to finish
Questions
How we track moratoria
Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.
What is a data center moratorium?
A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.