Northern Data has 3 campuses in 2 states: 1 operating and 2 planned or building, about 120 MW in the pipeline. Checked 27 Nov 2026

3Campuses
2States
≈120 MWIn the pipeline
0Moved in the last 90 days

Footprint

United StatesOpen map
One or two campusesThree or more

Every campus

GA1Maysville, GASite permitAug 2025120 MWNorthern Data: MaysvilleJackson County, GAConstructionApr 2025HPC data centerAllegheny County, PAOperating
Source filings, power and grid detail for all 3 Northern Data campusesFilings and grid detailStart Pro · $299/mo
Who works with Northern Data
  • Contractors and engineers across their sites
  • Tenants
  • Utilities and grid requests
Contractors, tenants and utilities for every Northern Data campusOpen the app, freeStart Pro · $299/mo

Know when Northern Data files something

Check your email to finish

Questions

How many data centers does Northern Data have?

As of 2026-11-27, Wattlas lists 3 US data center campuses associated with Northern Data: 2 confirmed pipeline campuses (1 under construction), 1 operating sites, and 0 tracker-reported plans.

Where is it building?