An estimated 80–360 MW data center campus in Hilliard, Ohio, built by Amazon. It has had a site permit since September 2017 and has 2 public records behind it. Checked 27 Nov 2026
Site permitStage since Sep 2017
≈80–360 MWCapacity, our estimate
2Public records
15Moratoria nearby
How far along
- Announced
- Zoning
- Site permitSep 2017
- Building permit
- Construction
- Operating
The site permit dates from September 2017. A building permit is the next step. Grove City has a moratorium in force 12 km away
Franklin County, OhioParcel, substation and lines
The record
- Owner
- Amazon
- County
- Franklin County, OH
- Stage
- Site permit
- Capacity
- ≈80–360 MW
- Public records
- 2
- Latest record
- 1 Sep 2017
- Opposition
- 13 moratoria in force and 2 ended nearby
Power and grid
- Utility
- Substation
- County queue
Site
- Exact location
- Parcel
- Water stress, flood
Who is on it
- Tenant
- Contractors
- Companies involved
2 records
- Record 1
- Record 2
Utility, substation and 2 public records for AWS Hayden Run Campus (CMH052)Open the app, freeStart Pro · $299/mo
Opposition nearby
Grove City moratorium12 kmIn forceJackson Township (Franklin County) moratorium13 kmIn forcePrairie Township (Franklin County) moratorium16 kmIn forcePleasant Township (Franklin County) moratorium19 kmIn force
Opposition in OhioKnow when this campus moves
Check your email to finish
Questions
Who owns AWS Hayden Run Campus (CMH052)?
Amazon, according to public records.
How big is it?
About 80–360 MW. This is our estimate from permitted sq ft, not a stated figure.
Has it been approved?
Yes. It has had a site permit since September 2017.
Is there local opposition?
Yes. 13 moratoria in force and 2 ended nearby.