Gcth I
Bank of America - RTX Modular Data Center
An estimated 22–100 MW data center campus in Richardson, Texas, built by Gcth I. It has had a site permit since June 2018 and has 1 public record behind it. Checked 27 Nov 2026
Site permitStage since Jun 2018
≈22–100 MWCapacity, our estimate
1Public records
How far along
- Announced
- Zoning
- Site permitJun 2018
- Building permit
- Construction
- Operating
The site permit dates from June 2018. A building permit is the next step
Collin County, TexasParcel, substation and lines
The record
- Owner
- Gcth I
- County
- Collin County, TX
- Stage
- Site permit
- Capacity
- ≈22–100 MW
- Public records
- 1
- Latest record
- 1 Jun 2018
- Opposition
- None on record
Power and grid
- Utility
- Substation
- County queue
Site
- Exact location
- Parcel
- Water stress, flood
Who is on it
- Tenant
- Contractors
- Companies involved
1 record
- Record 1
Utility, substation and 1 public record for Bank of America - RTX Modular Data CenterOpen the app, freeStart Pro · $299/mo
Know when this campus moves
Check your email to finish
Questions
Who owns Bank of America - RTX Modular Data Center?
Gcth I, according to public records.
How big is it?
About 22–100 MW. This is our estimate from site acreage, not a stated figure.
Has it been approved?
Yes. It has had a site permit since June 2018.
Is there local opposition?
Not on record