Beale Project Pilot Data Center

A 600 MW data center campus in De Soto, Kansas, built by Beale Infrastructure. It has been announced and has 13 public records behind it. Checked 27 Nov 2026

AnnouncedStage
600 MWCapacity, as stated
13Public records
30Moratoria nearby

How far along

  1. Announced
  2. Zoning
  3. Site permit
  4. Building permit
  5. Construction
  6. Operating

Publicly announced by the developer, a utility or local officials, with no land-use filing found yet. A rezoning or site permit is the next step. Miami County has a moratorium in force 36 km away

Johnson County, KansasParcel, substation and lines

The record

Stage
Announced
Capacity
600 MW
Public records
13
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
13 records
  • Record 1
  • Record 2
  • Record 3
Utility, substation and 13 public records for Beale Project Pilot Data CenterOpen the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns Beale Project Pilot Data Center?
Beale Infrastructure, according to public records.
How big is it?
600 MW, as stated in a public filing.
Has it been approved?
Not yet. It has been announced.
Is there local opposition?
Yes. 26 moratoria in force and 4 ended nearby.