A 190 MW data center campus in Clifton, Texas, built by CyrusOne. It has been under construction since March 2026 and has 26 public records behind it. Checked 27 Nov 2026
ConstructionStage since Mar 2026
190 MWCapacity, as stated
26Public records
How far along
- Announced
- Zoning
- Site permit
- Building permit
- ConstructionMar 2026
- Operating
The construction dates from March 2026. Operating is the next step
Bosque County, TexasParcel, substation and lines
The record
Know when this campus moves
Check your email to finish
Questions
Who owns CyrusOne DFW10?
CyrusOne, according to public records.
How big is it?
190 MW, as stated in a public filing.
Has it been approved?
Yes. It has been under construction since March 2026.
Is there local opposition?
Not on record