DataBank MSP3 Data Center

A 9 MW data center campus in Brooklyn Park, Minnesota, built by DataBank. It has had a building permit since January 2024 and has 4 public records behind it. Checked 27 Nov 2026

Building permitStage since Jan 2024
9 MWCapacity, as stated
4Public records
2Moratoria in force nearby

How far along

  1. Announced
  2. Zoning
  3. Site permit
  4. Building permitJan 2024
  5. Construction
  6. Operating

The building permit dates from January 2024. Construction is the next step. Plymouth has a moratorium in force 1 km away

Hennepin County, MinnesotaParcel, substation and lines

The record

Stage
Building permit
Capacity
9 MW
Public records
4
Latest record
1 Jan 2024
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
4 records
  • Record 1
  • Record 2
  • Record 3
Utility, substation and 4 public records for DataBank MSP3 Data CenterOpen the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns DataBank MSP3 Data Center?
DataBank, according to public records.
How big is it?
9 MW, as stated in a public filing.
Has it been approved?
Yes. It has had a building permit since January 2024.
Is there local opposition?
Yes. 2 moratoria in force nearby.