An estimated 57–120 MW data center campus in Douglasville, Georgia, built by Microsoft. It has had a building permit since March 2023 and has 6 public records behind it. Checked 27 Nov 2026
Building permitStage since Mar 2023
≈57–120 MWCapacity, our estimate
6Public records
2Opposition records
How far along
- Announced
- Zoning
- Site permit
- Building permitMar 2023
- Construction
- Operating
The building permit dates from March 2023. Construction is the next step
Douglas County, GeorgiaParcel, substation and lines
The record
- Owner
- Microsoft
- County
- Douglas County, GA
- Stage
- Building permit
- Capacity
- ≈57–120 MW
- Public records
- 6
- Latest record
- 13 Sep 2024
- Opposition
- 2 opposition records
Power and grid
- Utility
- Substation
- County queue
Site
- Exact location
- Parcel
- Water stress, flood
Who is on it
- Tenant
- Contractors
- Companies involved
6 records
- Record 1
- Record 2
- Record 3
Know when this campus moves
Check your email to finish
Questions
Who owns FTY01 Data Center?
Microsoft, according to public records.
How big is it?
About 57–120 MW. This is our estimate from backup generators, not a stated figure.
Has it been approved?
Yes. It has had a building permit since March 2023.
Is there local opposition?
Yes. 2 opposition records on file.