A 280 MW data center campus in McCamey, Texas, built by Fowler Johns. It has had a site permit since March 2022 and has 5 public records behind it. Checked 27 Nov 2026
Site permitStage since Mar 2022
280 MWCapacity, as stated
5Public records
How far along
- Announced
- Zoning
- Site permitMar 2022
- Building permit
- Construction
- Operating
The site permit dates from March 2022. A building permit is the next step
Upton County, TexasParcel, substation and lines
The record
- Owner
- Fowler Johns
- County
- Upton County, TX
- Stage
- Site permit
- Capacity
- 280 MW
- Public records
- 5
- Latest record
- Sep 2026
- Opposition
- None on record
Power and grid
- Utility
- Substation
- County queue
Site
- Exact location
- Parcel
- Water stress, flood
Who is on it
- Tenant
- Contractors
- Companies involved
5 records
- Record 1
- Record 2
- Record 3
Utility, substation and 5 public records for King Mountain Data Center - NE SiteOpen the app, freeStart Pro · $299/mo
Know when this campus moves
Check your email to finish
Questions
Who owns King Mountain Data Center - NE Site?
Fowler Johns, according to public records.
How big is it?
280 MW, as stated in a public filing.
Has it been approved?
Yes. It has had a site permit since March 2022.
Is there local opposition?
Not on record