Microsoft Corporation - Yellow Facility

An estimated 74–340 MW data center campus in Annapolis Junction, Maryland, built by Microsoft. It has had a site permit since February 2025 and has 1 public record behind it. Checked 27 Nov 2026

Site permitStage since Feb 2025
≈74–340 MWCapacity, our estimate
1Public records
17Moratoria nearby

How far along

  1. Announced
  2. Zoning
  3. Site permitFeb 2025
  4. Building permit
  5. Construction
  6. Operating

The site permit dates from February 2025. A building permit is the next step. Anne Arundel County has a moratorium pending 2 km away

Anne Arundel County, MarylandParcel, substation and lines

The record

County
Anne Arundel County, MD
Stage
Site permit
Capacity
≈74–340 MW
Public records
1
Latest record
13 Feb 2025
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
1 record
  • Record 1
Utility, substation and 1 public record for Microsoft Corporation - Yellow FacilityOpen the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns Microsoft Corporation - Yellow Facility?
Microsoft, according to public records.
How big is it?
About 74–340 MW. This is our estimate from site acreage, not a stated figure.
Has it been approved?
Yes. It has had a site permit since February 2025.
Is there local opposition?
Yes. 15 moratoria in force and 1 pending and 1 ended nearby.