NTT Data Center

A 240 MW data center campus in Mesa, Arizona, built by NTT. It has had a building permit since February 2025 and has 2 public records behind it. Checked 27 Nov 2026

Building permitStage since Feb 2025
240 MWCapacity, as stated
2Public records

How far along

  1. Announced
  2. Zoning
  3. Site permit
  4. Building permitFeb 2025
  5. Construction
  6. Operating

The building permit dates from February 2025. Construction is the next step

Maricopa County, ArizonaParcel, substation and lines

The record

Owner
NTT
Stage
Building permit
Capacity
240 MW
Public records
2
Latest record
31 Oct 2025
Opposition
None on record
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
2 records
  • Record 1
  • Record 2
Utility, substation and 2 public records for NTT Data CenterOpen the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns NTT Data Center?
NTT, according to public records.
How big is it?
240 MW, as stated in a public filing.
Has it been approved?
Yes. It has had a building permit since February 2025.
Is there local opposition?
Not on record