Platon Investments
Platon Site
An estimated 640–3,000 MW data center campus in Wilbarger County, Texas, built by Platon Investments. It has had a site permit since May 2026 and has 1 public record behind it. Checked 27 Nov 2026
Site permitStage since May 2026
≈640–3,000 MWCapacity, our estimate
1Public records
How far along
- Announced
- Zoning
- Site permitMay 2026
- Building permit
- Construction
- Operating
The site permit dates from May 2026. A building permit is the next step
Wilbarger County, TexasParcel, substation and lines
The record
- Owner
- Platon Investments
- County
- Wilbarger County, TX
- Stage
- Site permit
- Capacity
- ≈640–3,000 MW
- Public records
- 1
- Latest record
- 5 May 2026
- Opposition
- None on record
Power and grid
- Utility
- Substation
- County queue
Site
- Exact location
- Parcel
- Water stress, flood
Who is on it
- Tenant
- Contractors
- Companies involved
1 record
- Record 1
Know when this campus moves
Check your email to finish
Questions
Who owns Platon Site?
Platon Investments, according to public records.
How big is it?
About 640–3,000 MW. This is our estimate from site acreage, not a stated figure.
Has it been approved?
Yes. It has had a site permit since May 2026.
Is there local opposition?
Not on record