Quantum Campus

An estimated 170–760 MW data center campus in Haskell County, Texas, built by Google. It has had a site permit since May 2025 and has 9 public records behind it. Checked 27 Nov 2026

Site permitStage since May 2025
≈170–760 MWCapacity, our estimate
9Public records

How far along

  1. Announced
  2. Zoning
  3. Site permitMay 2025
  4. Building permit
  5. Construction
  6. Operating

The site permit dates from May 2025. A building permit is the next step

Haskell County, TexasParcel, substation and lines

The record

Owner
Google
County
Haskell County, TX
Stage
Site permit
Capacity
≈170–760 MW
Public records
9
Latest record
5 Feb 2026
Opposition
None on record
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
9 records
  • Record 1
  • Record 2
  • Record 3
Utility, substation and 9 public records for Quantum CampusOpen the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns Quantum Campus?
Google, according to public records.
How big is it?
About 170–760 MW. This is our estimate from site acreage, not a stated figure.
Has it been approved?
Yes. It has had a site permit since May 2025.
Is there local opposition?
Not on record