T5@ATL IV

A 300 MW data center campus in Coweta County, Georgia, built by T5. It has had a rezoning request on file since September 2023 and has 2 public records behind it. Checked 27 Nov 2026

ZoningStage since Sep 2023
300 MWCapacity, as stated
2Public records
7Moratoria nearby

How far along

  1. Announced
  2. ZoningSep 2023
  3. Site permit
  4. Building permit
  5. Construction
  6. Operating

The zoning dates from September 2023. Zoning approval is the next step. Coweta County has a moratorium in force 1 km away

Coweta County, GeorgiaParcel, substation and lines

The record

Owner
T5
County
Coweta County, GA
Stage
Zoning
Capacity
300 MW
Public records
2
Latest record
28 Sep 2023
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
2 records
  • Record 1
  • Record 2
Utility, substation and 2 public records for T5@ATL IVOpen the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns T5@ATL IV?
T5, with T5 Atlanta IV also named, according to public records.
How big is it?
300 MW, as stated in a public filing.
Has it been approved?
Not yet. It has had a rezoning request on file since September 2023.
Is there local opposition?
Yes. 2 moratoria in force and 5 ended nearby.