Vantage Data Center - Doughlasville

An estimated 210–970 MW data center campus in Douglas County, Georgia, built by Vantage. It has had a rezoning request on file since August 2023 and has 4 public records behind it. Checked 27 Nov 2026

ZoningStage since Aug 2023
≈210–970 MWCapacity, our estimate
4Public records
2Opposition records

How far along

  1. Announced
  2. ZoningAug 2023
  3. Site permit
  4. Building permit
  5. Construction
  6. Operating

The zoning dates from August 2023. Zoning approval is the next step

Douglas County, GeorgiaParcel, substation and lines

The record

Owner
Vantage
Stage
Zoning
Capacity
≈210–970 MW
Public records
4
Latest record
15 Aug 2023
Power and grid
  • Utility
  • Substation
  • County queue
Site
  • Exact location
  • Parcel
  • Water stress, flood
Who is on it
  • Tenant
  • Contractors
  • Companies involved
4 records
  • Record 1
  • Record 2
  • Record 3
Utility, substation and 4 public records for Vantage Data Center - DoughlasvilleOpen the app, freeStart Pro · $299/mo

Know when this campus moves

Check your email to finish

Questions

Who owns Vantage Data Center - Doughlasville?
Vantage, according to public records.
How big is it?
About 210–970 MW. This is our estimate from permitted sq ft, not a stated figure.
Has it been approved?
Not yet. It has had a rezoning request on file since August 2023.
Is there local opposition?
Yes. 2 opposition records on file.