Central & Eastern Iowa
Central & Eastern Iowa is market 17 of 34: about 3.6 GW across 10 campuses in 8 counties. 3 under construction and 1 moratorium in force. Checked 28 Nov 2026
Largest campuses
All 10 campuses
The shape of the market
By stage
- Announced2
- Zoning1
- Site permit4
- Construction3
Stated and estimated
- Stated on recordNot on record
- Our estimate≈3.6 GW
Who is building
MicrosoftNot on record3
Tract1,000 MW1
CyrusOne24 MW1
Edged13 MW1- Clop Des Moines IA5 MW1
What could slow it
- Utilities serving these campuses
- Grid requests on file
- Substations, water stress and flood
- Download this market as CSV
Track Central & Eastern Iowa in the app, free
Questions
How many data centers are in Central & Eastern Iowa?
11 tracked pipeline campuses (3.6 GW estimated total, 0 MW reported) across 8 counties in Iowa. Key signals: 4 sites showing earthwork in satellite imagery, 2 active/extended moratoria.
Estimated pipeline MW combines reported capacity (0 MW) with estimates from floor area, acreage, investment or backup generation. 44.4% of monitored sites show clearing.
Who is building the most?
Which counties have paused new data centers?
1 moratorium is in force in Central & Eastern Iowa, covering 2 campuses. 3 moratoria and 4 petitions are on record across the market. 0 of 11 campuses sit in high water stress.
How is this market drawn?
How large is the Central & Eastern Iowa data center pipeline?
Wattlas tracks 11 upcoming pipeline campuses in Central & Eastern Iowa (7 verified, 3 under construction, 5 permitted), representing 0 MW in reported capacity and 3,637 MW total estimated pipeline. Projects with the largest reported figures include QTS Cedar Rapids Data Center Campus (1,000+ MW), Tract Altoona (1,000+ MW), Google Cedar Rapids Data Center Campus (500–999 MW).
What are industrial power rates and serving utilities in Central & Eastern Iowa?
Central & Eastern Iowa sits in MISO. Industrial power rates, serving utilities, substation and transmission distance, large-load tariffs and interconnection queue depth for every tracked site are included in Wattlas access.
What local opposition, moratoria, or water risks affect Central & Eastern Iowa data centers?
Across tracked campuses in Central & Eastern Iowa, Wattlas links 2 active or extended moratoria (3 total) and 4 public petitions. On physical site risk, 0 of 11 pipeline campuses sit in High or Extremely High baseline water stress (0 Extremely High). Floodplain and ozone screening are included in Wattlas access.
How many Central & Eastern Iowa data center sites show active satellite land clearing?
Of 9 pinpointed pipeline sites monitored with satellite imagery in Central & Eastern Iowa, 4 (44.4%) show active earthwork or pad expansion, including 3 sites clearing ahead of a reported construction stage.