Minneapolis-St. Paul & SE MN
Minneapolis-St. Paul & SE MN is market 12 of 34: about 6.0 GW across 56 campuses in 13 counties. 1 under construction and 7 moratoria in force. Checked 28 Nov 2026
Largest campuses
All 56 campuses
The shape of the market
By stage
- Announced40
- Site permit12
- Building permit3
- Construction1
Stated and estimated
- Stated on record1.0 GW
- Our estimate≈5.0 GW
Who is building
Google2,560 MW3
DataBank29 MW2
Compass10 MW2
Wells Fargo Bank N A6 MW2
General MillsNot on record2
By county
- Hennepin19
- Dakota13
- Carver5
- Ramsey5
- Washington3
What could slow it
- Utilities serving these campuses
- Grid requests on file
- Substations, water stress and flood
- Download this market as CSV
Track Minneapolis-St. Paul & SE MN in the app, free
Questions
How many data centers are in Minneapolis-St. Paul & SE MN?
62 tracked pipeline campuses (6.0 GW estimated total, 1,000 MW reported) across 13 counties in Minnesota. Key signals: 16 sites showing earthwork in satellite imagery, 8 active/extended moratoria, 22 pipeline sites in high/extremely high water stress.
Estimated pipeline MW combines reported capacity (1,000 MW) with estimates from floor area, acreage, investment or backup generation. 36.4% of monitored sites show clearing.
Who is building the most?
Which counties have paused new data centers?
7 moratoria are in force in Minneapolis-St. Paul & SE MN, covering 24 campuses. 9 moratoria and 6 petitions are on record across the market. 22 of 62 campuses sit in high water stress.
How is this market drawn?
How large is the Minneapolis-St. Paul & SE MN data center pipeline?
Wattlas tracks 62 upcoming pipeline campuses in Minneapolis-St. Paul & SE MN (15 verified, 1 under construction, 19 permitted), representing 1,000 MW in reported capacity and 6,003 MW total estimated pipeline. Projects with the largest reported figures include Google Hermantown Data Center (1,000+ MW), Google Pine Island Campus (500–999 MW), Project Skyway - Phase 1 (500–999 MW).
What are industrial power rates and serving utilities in Minneapolis-St. Paul & SE MN?
Minneapolis-St. Paul & SE MN sits in MISO. Industrial power rates, serving utilities, substation and transmission distance, large-load tariffs and interconnection queue depth for every tracked site are included in Wattlas access.
What local opposition, moratoria, or water risks affect Minneapolis-St. Paul & SE MN data centers?
Across tracked campuses in Minneapolis-St. Paul & SE MN, Wattlas links 8 active or extended moratoria (9 total) and 6 public petitions. On physical site risk, 22 of 62 pipeline campuses sit in High or Extremely High baseline water stress (3 Extremely High). Floodplain and ozone screening are included in Wattlas access.
How many Minneapolis-St. Paul & SE MN data center sites show active satellite land clearing?
Of 44 pinpointed pipeline sites monitored with satellite imagery in Minneapolis-St. Paul & SE MN, 16 (36.4%) show active earthwork or pad expansion, including 15 sites clearing ahead of a reported construction stage.