ProposedMoratorium

Amherst moratorium

Amherst, Ohio has proposed a pause on new data center approvals, citing specific project and zoning and rules. It covers 2 tracked campuses. Checked 23 Nov 2026

The facts

Applies to
Proposed 45 MW data center at the Nordson property (variance rejected by the Board of Zoning Appeals).
Reason
Opposition to a proposed 45-megawatt data center at the Nordson property, which needed a zoning variance (BZA hearing, late July 2026); industrial zoning code review underway.
Term
Proposal amended September 28, 2026 to end December 31, 2027 with no automatic six-month extension; subsequent disposition unresolved.
Legal basis
Proposed City of Amherst (Lorain County) legislation (sponsored by Ward 1 Council member Brian Dembinski) prohibiting data centers larger than 2.5 MW during zoning review
What happened next
Pause on data centers above 2.5 MW while the industrial zoning code review committee updates regulations.

Know when Amherst votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (2 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near Amherst paused data centers?