In forceMoratorium

North Ridgeville moratorium

North Ridgeville, Ohio paused new data center approvals on 18 May 2026, citing zoning and rules and water use. Checked 23 Nov 2026

In force since 18 May 2026No end date on record

The facts

Applies to
None. No developer had approached the city.
Term
Up to 12 months
Reason
Preemptive. National growth of AI/cloud data centers. Demand on water and wastewater systems: the city-owned wastewater plant could need major upgrades. Wanted to block applications before regulations exist.
Legal basis
City of North Ridgeville Ordinance No. 2026-57 (emergency), a 12-month moratorium on planning, zoning and building approvals for data centers, cryptocurrency-mining facilities and similar uses
What happened next
Administration to analyze infrastructure capacity and zoning approaches and recommend code changes, with public hearings, before the pause ends.

Know when North Ridgeville votes

Check your email to finish

Questions

How we track moratoria

Moratorium records come from public records, filtered to data center ordinances and resolutions. Records are matched to Wattlas campuses by exact city or county within the same state. Linked campuses (0 here) counts the Wattlas campuses matched to this measure. Campuses in reach are the closest tracked sites by straight-line distance.

What is a data center moratorium?

A local pause on accepting or approving new data center applications, usually for a set term while the city or county rewrites its zoning, water or power rules. Projects already approved often keep going.

Which other places near North Ridgeville paused data centers?